Maple Creek Drainage Pump Station

The Cit is replacing a 1990 pump station with a higher-capacity, fish-friendly facility to protect neighbourhoods during heavy rain and support a healthier creek.

  • Status: Under construction
  • Construction: Began 2025
  • Completion: Anticipated 2027
  • Estimated cost: $14M total construction

Project Overview

Replacing an ageing pump station

The Maple Creek Drainage Pump Station was built in 1990 and is now in very poor condition, with structural and electrical issues as well as limitations in capacity, safety, and fish passage. The City is replacing it with a modern facility that can handle greater flows during major storms.

The existing pump style is also not fish passable. The new design will add pumping capacity while allowing fish to pass safely, supporting a healthier Maple Creek alongside stronger flood protection. These upgrades were recommended in the 2021 Maple Creek Integrated Watershed Management Plan.

How it works

A fish-friendly upgrade

Because much of Port Coquitlam sits on low, flat land near the Coquitlam and Pitt rivers, pump stations move stormwater away from neighbourhoods so it can drain safely. The upgraded Maple Creek station adds pumping capacity for heavy rain and uses a fish-passable design, so fish can move safely while the community stays protected.

Image

What the upgrade includes

Site Works

Preparing and improving the pump station site

Pump replacement and upgrade

Pump replacement and upgrade

New piping and valves

Updated pipes and vales to move water reliably

Electrical upgrades

Renewed electrical systems for safe operation

Permanent generator

Backup power to keep the station running

Flap gate and inlet grill

Replacement of the flap and inlet grill

Community benefits

  • Stronger flood protection: Added pumping capacity helps the drainage system keep pace during significant rain events, protecting nearby homes, streets, and property
  • A healthier creek: A fish-passable design replaces a pump that fish cannot pass, supporting ecological health in Maple Creek while improving drainage
  • Reliable, modern equipment: Replacing a station in very poor condition, and including a permanent back-up generator, reduces the risk of failures and service interruptions

Project Timeline

  • Recommended in the Maple Creek IWMP (2021)
    • Upgrades to the pump station were identified in the 2021 Maple Creek Integrated Watershed Management Plan.
  • Preliminary Design (2023)
    • Early design work assessed the condition of the station and the upgrades required.
  • Detailed Design (2024)
    • Design was advanced to prepare the project for construction.
  • Construction (Current Phase: Began 2025)
    • Construction of the replacement pump station is underway, supported by confirmed federal funding.
  • Completion (Anticipated Early 2027)
    • The upgraded, fish-passable station will be commissioned and returned to full operation.

Project Renderings

See what the replacement station will look like once complete.

Image
Maple Creek Drainage Pump Station
Image
Image
Image

Project Documents

Maple Creek & Coquitlam River Pump Station Map

View the location of the pump station and related drainage infrastructure.

Capital project signage

See the on-site project sign, with a summary of the work taking place.

May 2025 Public Information Letter

The letter shared with nearby residents about the project and construction.

Funding

This project is funded in part by the Government of Canada. This project is a shared investment in the community. Investing in core infrastructure like this helps keep the community safe and resilient for years to come.