The Cit is replacing a 1990 pump station with a higher-capacity, fish-friendly facility to protect neighbourhoods during heavy rain and support a healthier creek.
- Status: Under construction
- Construction: Began 2025
- Completion: Anticipated 2027
- Estimated cost: $14M total construction
Project Overview
Replacing an ageing pump station
The Maple Creek Drainage Pump Station was built in 1990 and is now in very poor condition, with structural and electrical issues as well as limitations in capacity, safety, and fish passage. The City is replacing it with a modern facility that can handle greater flows during major storms.
The existing pump style is also not fish passable. The new design will add pumping capacity while allowing fish to pass safely, supporting a healthier Maple Creek alongside stronger flood protection. These upgrades were recommended in the 2021 Maple Creek Integrated Watershed Management Plan.
How it works
A fish-friendly upgrade
Because much of Port Coquitlam sits on low, flat land near the Coquitlam and Pitt rivers, pump stations move stormwater away from neighbourhoods so it can drain safely. The upgraded Maple Creek station adds pumping capacity for heavy rain and uses a fish-passable design, so fish can move safely while the community stays protected.

What the upgrade includes
Site Works
Pump replacement and upgrade
New piping and valves
Electrical upgrades
Permanent generator
Flap gate and inlet grill
Community benefits
- Stronger flood protection: Added pumping capacity helps the drainage system keep pace during significant rain events, protecting nearby homes, streets, and property
- A healthier creek: A fish-passable design replaces a pump that fish cannot pass, supporting ecological health in Maple Creek while improving drainage
- Reliable, modern equipment: Replacing a station in very poor condition, and including a permanent back-up generator, reduces the risk of failures and service interruptions
Project Timeline
- Recommended in the Maple Creek IWMP (2021)
- Upgrades to the pump station were identified in the 2021 Maple Creek Integrated Watershed Management Plan.
- Preliminary Design (2023)
- Early design work assessed the condition of the station and the upgrades required.
- Detailed Design (2024)
- Design was advanced to prepare the project for construction.
- Construction (Current Phase: Began 2025)
- Construction of the replacement pump station is underway, supported by confirmed federal funding.
- Completion (Anticipated Early 2027)
- The upgraded, fish-passable station will be commissioned and returned to full operation.
Project Renderings
See what the replacement station will look like once complete.
Project Documents
Maple Creek & Coquitlam River Pump Station Map
May 2025 Public Information Letter
Funding
This project is funded in part by the Government of Canada. This project is a shared investment in the community. Investing in core infrastructure like this helps keep the community safe and resilient for years to come.